The following is an update
to the Short-Term Operational Plan for the pipe maintenance on
the NPS 36 Foothills BC Mainline.
Effective November 17 at
08:00 MST, the receipts onto the BC system at the Alberta BC border
will be reduced to 54.5 E6m3/d. The typical demand at the Alberta
BC border has ranged from 30 to 62 E6m3/d in recent weeks. NGTL
FT service levels as of November 1 are 76.1 E6m3/d (2702 mmcf/d)
at ALTBC Border.
The reduction in capability
is required to perform a pipe replacement on a section of pipe
that was recently inspected as part of TransCanada's pipeline
integrity program.
The above outage is anticipated
to be completed on November 20 at 17:00 MST, but may take longer
due to factors such as the weather and the challenging location.
Further updates regarding
this maintenance work will be provided via bulletin. For more
information, please contact (403) 920-PIPE.