For gas day August 3,
2006, TransCanada will be performing an inline inspection on the
NPS 36 Foothills BC M/L. Effective at 08:00 MST, the receipt
capacity of the BC System at the Alberta/BC border will be reduced
to 58.0 10 6 m3/d (2047 MMcf/d). Recent demand at the Alberta/BC
Border has ranged from 60 10 6 m3/d (2118 MMcf/d) to 69 10 6 m3/d
(2436 MMcf/d). The outage is expected to be completed within
24 hours.
The inline inspection
is part of TransCanada's ongoing maintenance program, aimed at
bringing the currently de-rated pipeline back to is full Maximum
Allowable Operating Pressure as soon as possible.
Further information
will be provided when available.
For more information
, please contact the PipeLine at 403-920-7473, or Toll Free
at 1-877-920-7473.