Gas
Transmission Northwest (GTN) hereby gives notice of the expiration,
on October 31, 2006, of capacity that is currently under long-term
firm service agreements that carry Right of First Refusal ("ROFR")
rights.
Consistent
with Paragraph 33.2 of GTN's tariff (“Tariff”), some current capacity
holders with firm transportation agreements expiring October 31,
2006 have elected to enter the ROFR process. The
volumes are shown in aggregate in the table below. Pursuant
to the ROFR process outlined in Paragraph
33.2 of the Tariff, GTN will offer individual parcels of this
capacity via open bidding at least three months prior to November
1, 2006, the earliest start date of new firm transportation agreements
for this capacity. Bids accepted by GTN for this capacity will
be subject to match by the current capacity holder(s).
Kingsgate
to Malin: 15,000
Dth/d
Kingsgate
to Stanfield: 130,715 Dth/d
Stanfield
to Malin:
141,708 Dth/d
Consistent
with Paragraph 33.1 of the Tariff, some current capacity holders
have elected to terminate firm transportation agreements on October
31, 2006 as shown in aggregate in the table below. GTN will offer
individual parcels of this capacity for sale via an open season
at least three months prior to November 1, 2006, the earliest
start date of new firm transportation agreements for this capacity.
Bids accepted by
GTN for this capacity will not be subject to match by the
current capacity holder(s).
Kingsgate
to Stanfield: 83,085 Dth/d
All
foregoing capacity that is not renewed by the existing shipper,
and is purchased for a term equal to or greater than one year,
is subject to GTN's incremental fuel surcharge.