At approximately 3:15
pm on April 5th, TransCanada experienced a fire at its Elko A
C/S facility. The A unit's failure has resulted in the temporary
shut down and unavailability of the entire ELKO C/S. With
this Station unavailable, the receipt capacity of the BC System
is reduced to approximately 2118 MMcf/d (60 10
6m3/d or 2,268,000 GJ). Current nominated
flow on the BC System is between 1518 to 1765 MMcf/d.
Investigation into the
cause of the fire is ongoing. However, TransCanada expects
that the other two units, B and C, may return to service by next
week.
Further updates will
follow as more information becomes available.
For further information
please contact The Pipeline at (403) 920-7473 or 1-877-920-7473