The throughput limitation
at the Station 9 A and B units has been corrected and the ability
to make deliveries through the southern portion of the GTN system
has been restored. Therefore, beginning with the Intra-day
2 scheduling cycle for gas day Monday, August 28, 2006, the capacity
through Station 14 will be restated to 2050 MMcf/d.
If you have any questions, please call GTN's Gas Transportation
Coordinator at 503.833.4300,
Option 1.